Standing in the downstairs family room, looking toward the boys' rooms. The next steps are laying eco-foam over the gravel, then laying the blue water barrier from wall to wall, completely covering the gravel and sub-foundation with an insulated, water-tight membrane. After that, the cement foundation will be poured -- hopefully on Friday -- and then covered with cardboard to protect it during the remaining building process, until we seal it.
The grey part of the wall is the mostly finished version; the holes in it are for our exterior stairway lighting.
This big walkway will all be backfilled with dirt after the perf-board (for drainage) is installed.
Tidak ada komentar:
Posting Komentar
Catatan: Hanya anggota dari blog ini yang dapat mengirim komentar.